NO.  ITEM  UNIT  QUANTITY                                                     
   Tidewater Utility Construc               Walter C. Via         Jamestown Contractor     Henderson Inc      J Sanders Construction      Franklin Mechanical      Suburban Grading      Basic Construction      M & W Construction   Chesapeake Bay Contractors   VICO Construction Corp.   T. A. Sheets     Total Engineering 
1 Mobilization (5% of total price of all other bid items)  LS  1  $186,033.50  $          186,033.50  $  75,000.00  $          75,000.00  $100,000.00  $     100,000.00  $137,209.00  $    137,209.00  $  28,000.00  $         28,000.00  $196,530.50  $  196,530.50  $225,000.00  $       225,000.00  $  54,800.00  $          54,800.00  $112,000.00  $       112,000.00  $215,000.00  $        215,000.00  $  91,596.00  $             91,596.00  $  50,000.00  $       50,000.00  $117,986.17  $      117,986.17
2 Undercut Excavation with Bedding Backfill  CY  1,000  $          0.01  $                  10.00  $        19.00  $          19,000.00  $        30.00  $       30,000.00  $        65.39  $     65,390.00  $          0.01  $               10.00  $        35.00  $    35,000.00  $        60.00  $         60,000.00  $        69.80  $          69,800.00  $        91.00  $         91,000.00  $        90.00  $          90,000.00  $        18.60  $             18,600.00  $        38.00  $       38,000.00  $        64.51  $       64,510.00
3 Select Material - Sand  Ton  9,000  $          0.01  $                  90.00  $        22.00  $        198,000.00  $          6.25  $       56,250.00  $          1.00  $       9,000.00  $          0.01  $               90.00  $        15.00  $  135,000.00  $          0.01  $               90.00  $        17.40  $        156,600.00  $        15.25  $       137,250.00  $        42.00  $        378,000.00  $        23.50  $           211,500.00  $          0.01  $             90.00  $          9.07  $       81,630.00
4 Select Material - Stone  Ton  9,000  $          0.01  $                  90.00  $        23.00  $        207,000.00  $          6.25  $       56,250.00  $          1.00  $       9,000.00  $          0.01  $               90.00  $        25.00  $  225,000.00  $          0.01  $               90.00  $        27.20  $        244,800.00  $        37.00  $       333,000.00  $        55.00  $        495,000.00  $        39.00  $           351,000.00  $          0.01  $             90.00  $        21.74  $      195,660.00
5 Miscellaneous Unclassified Excavation as Directed by  CY  1,000  $          0.01  $                  10.00  $        12.00  $          12,000.00  $          5.00  $         5,000.00  $        13.30  $     13,300.00  $          0.01  $               10.00  $        20.00  $    20,000.00  $        25.00  $         25,000.00  $        61.90  $          61,900.00  $        20.00  $         20,000.00  $        42.00  $          42,000.00  $          8.50  $               8,500.00  $          0.01  $             10.00  $          9.40  $         9,400.00
6 Rock Check Dam  Each  5  $        50.00  $                 250.00  $        75.00  $               375.00  $        50.00  $           250.00  $      237.42  $       1,187.10  $        20.00  $             100.00  $      100.00  $         500.00  $      375.00  $          1,875.00  $      329.00  $            1,645.00  $    2,290.00  $         11,450.00  $    1,000.00  $           5,000.00  $      850.00  $               4,250.00  $        25.00  $            125.00  $      491.25  $         2,456.25
7 Temporary Silt Fence  LF  1,000  $          4.00  $              4,000.00  $          2.75  $            2,750.00  $          1.30  $         1,300.00  $          2.66  $       2,660.00  $          1.00  $          1,000.00  $          4.00  $      4,000.00  $          4.00  $          4,000.00  $          2.40  $            2,400.00  $          2.00  $           2,000.00  $          2.00  $           2,000.00  $          2.50  $               2,500.00  $          1.00  $         1,000.00  $          3.00  $         3,000.00
8 Temporary Silt Fence With Wire Support  LF  3,000  $          6.00  $            18,000.00  $          4.00  $          12,000.00  $          2.20  $         6,600.00  $          4.32  $     12,960.00  $          4.00  $         12,000.00  $          7.00  $    21,000.00  $          5.00  $         15,000.00  $          3.20  $            9,600.00  $          2.25  $           6,750.00  $          3.50  $          10,500.00  $          4.90  $             14,700.00  $          3.00  $         9,000.00  $          5.00  $       15,000.00
9 Inlet Protection  Each  40  $      100.00  $              4,000.00  $        75.00  $            3,000.00  $        55.00  $         2,200.00  $      137.72  $       5,508.80  $          5.00  $             200.00  $      150.00  $      6,000.00  $      200.00  $          8,000.00  $        74.00  $            2,960.00  $      170.00  $           6,800.00  $      230.00  $           9,200.00  $      204.00  $               8,160.00  $        10.00  $            400.00  $      250.00  $       10,000.00
10 Tree Protection  LF  500  $          5.00  $              2,500.00  $          1.50  $               750.00  $          1.50  $           750.00  $          3.08  $       1,540.00  $          0.20  $             100.00  $        10.00  $      5,000.00  $          5.00  $          2,500.00  $          2.60  $            1,300.00  $          2.50  $           1,250.00  $          2.00  $           1,000.00  $          3.00  $               1,500.00  $          1.00  $            500.00  $          4.00  $         2,000.00
11 Aggregate Base Material  Ton  1,000  $        38.00  $            38,000.00  $        25.00  $          25,000.00  $        27.00  $       27,000.00  $        24.23  $     24,230.00  $        20.00  $         20,000.00  $        25.00  $    25,000.00  $        33.20  $         33,200.00  $        35.00  $          35,000.00  $        63.00  $         63,000.00  $        45.00  $          45,000.00  $        26.00  $             26,000.00  $        34.00  $       34,000.00  $        20.74  $       20,740.00
12 Base Overlay Prior to Construction  SY  5,000  $          6.00  $            30,000.00  $          8.00  $          40,000.00  $          7.00  $       35,000.00  $        11.92  $     59,600.00  $          5.50  $         27,500.00  $          8.00  $    40,000.00  $          7.50  $         37,500.00  $          8.50  $          42,500.00  $          8.00  $         40,000.00  $          8.30  $          41,500.00  $          8.20  $             41,000.00  $          8.00  $       40,000.00  $          8.34  $       41,700.00
13  Geotextile Fabrics  SY  4,000  $          3.00  $            12,000.00  $          3.00  $          12,000.00  $          1.50  $         6,000.00  $          2.07  $       8,280.00  $          1.00  $          4,000.00  $          1.25  $      5,000.00  $          2.50  $         10,000.00  $          2.10  $            8,400.00  $          1.25  $           5,000.00  $          2.50  $          10,000.00  $          4.40  $             17,600.00  $          5.00  $       20,000.00  $          2.24  $         8,960.00
14 Trench Repair Prior to Reconstruction  LF  9000  $          9.00  $            90,000.00  $        10.00  $          90,000.00  $          7.00  $       63,000.00  $        11.02  $     99,180.00  $          2.00  $         18,000.00  $          4.00  $    36,000.00  $        28.00  $       252,000.00  $          3.50  $          31,500.00  $          5.50  $         49,500.00  $          7.00  $          63,000.00  $        57.00  $           513,000.00  $          4.00  $       36,000.00  $          5.14  $       46,260.00
15  Improved Shoulder  LF  1,600  $        12.00  $            19,200.00  $        20.00  $          32,000.00  $          7.50  $       12,000.00  $        13.25  $     21,200.00  $          4.00  $          6,400.00  $        18.00  $    28,800.00  $        11.00  $         17,600.00  $        16.80  $          26,880.00  $        14.50  $         23,200.00  $        22.00  $          35,200.00  $        19.00  $             30,400.00  $        12.00  $       19,200.00  $          5.50  $         8,800.00
16 Asphalt Concrete Pavement Overlay  SY  5,000  $          8.00  $            40,000.00  $          8.00  $          40,000.00  $          8.00  $       40,000.00  $          5.94  $     29,700.00  $          7.00  $         35,000.00  $          7.50  $    37,500.00  $          7.10  $         35,500.00  $          8.40  $          42,000.00  $          7.50  $         37,500.00  $          8.30  $          41,500.00  $          8.20  $             41,000.00  $          6.50  $       32,500.00  $          8.34  $       41,700.00
17 Reconstructed Asphalt Pavement  SY  16,000  $        31.00  $          496,000.00  $        14.00  $        224,000.00  $        10.00  $     160,000.00  $        11.19  $    179,040.00  $          9.50  $       152,000.00  $        12.00  $  192,000.00  $          8.40  $       134,400.00  $        15.40  $        246,400.00  $          9.00  $       144,000.00  $        18.50  $        296,000.00  $        67.40  $         1,078,400.00  $          8.00  $     128,000.00  $        18.59  $      297,440.00
18 Concrete Driveway Restoration at Perpendicular  LF  70  $        50.00  $              3,500.00  $        65.00  $            4,550.00  $        50.00  $         3,500.00  $        85.39  $       5,977.30  $        15.00  $          1,050.00  $        50.00  $      3,500.00  $        83.49  $          5,844.30  $      240.00  $          16,800.00  $      108.00  $           7,560.00  $      130.00  $           9,100.00  $        84.00  $               5,880.00  $        45.00  $         3,150.00  $        24.98  $         1,748.60
19 Exposed Aggregate Concrete Driveway Restoration at  LF  30  $      100.00  $              3,000.00  $        95.00  $            2,850.00  $        50.00  $         1,500.00  $      156.53  $       4,695.90  $        25.00  $             750.00  $        60.00  $      1,800.00  $      106.25  $          3,187.50  $      533.00  $          15,990.00  $      158.00  $           4,740.00  $      160.00  $           4,800.00  $        92.00  $               2,760.00  $        70.00  $         2,100.00  $        32.98  $            989.40
20 Asphalt Driveway Restoration at Perpendicular Mainline or Lateral Crossing  LF  45  $        60.00  $              2,700.00  $        25.00  $            1,125.00  $        32.00  $         1,440.00  $        64.39  $       2,897.55  $        12.00  $             540.00  $        30.00  $      1,350.00  $        80.00  $          3,600.00  $      258.00  $          11,610.00  $        43.00  $           1,935.00  $        70.00  $           3,150.00  $        59.00  $               2,655.00  $        14.00  $            630.00  $        37.39  $         1,682.55
21 Concrete Driveway Restoration at Longitudinal Lateral Installation in Driveway  SY  50  $      150.00  $              7,500.00  $        80.00  $            4,000.00  $        50.00  $         2,500.00  $      132.74  $       6,637.00  $        45.00  $          2,250.00  $      200.00  $    10,000.00  $      123.63  $          6,181.50  $      273.00  $          13,650.00  $      152.00  $           7,600.00  $      130.00  $           6,500.00  $        79.00  $               3,950.00  $        75.00  $         3,750.00  $        56.20  $         2,810.00
22 Exposed Aggregate Concrete Driveway Restoration at Longitudinal Lateral Installation in Driveway  SY  50  $      150.00  $              7,500.00  $      100.00  $            5,000.00  $        50.00  $         2,500.00  $      138.14  $       6,907.00  $        70.00  $          3,500.00  $      230.00  $    11,500.00  $      159.38  $          7,969.00  $      282.00  $          14,100.00  $      209.00  $         10,450.00  $      165.00  $           8,250.00  $        82.00  $               4,100.00  $      100.00  $         5,000.00  $        56.20  $         2,810.00
23 Asphalt Driveway Restoration at Longitudinal Lateral Installation in Driveway  SY  113  $        50.00  $              5,650.00  $        22.00  $            2,486.00  $        15.00  $         1,695.00  $        52.59  $       5,942.67  $        12.00  $          1,356.00  $        20.00  $      2,260.00  $        60.10  $          6,791.30  $      122.00  $          13,786.00  $        42.00  $           4,746.00  $        85.00  $           9,605.00  $        66.00  $               7,458.00  $        20.00  $         2,260.00  $        29.54  $         3,338.02
24 Aggregate Driveway Restoration  Ton  240  $        38.00  $              9,120.00  $        22.00  $            5,280.00  $        25.00  $         6,000.00  $        29.00  $       6,960.00  $        14.00  $          3,360.00  $        30.00  $      7,200.00  $        33.20  $          7,968.00  $        55.40  $          13,296.00  $        59.00  $         14,160.00  $        50.00  $          12,000.00  $        30.00  $               7,200.00  $        50.00  $       12,000.00  $        21.74  $         5,217.60
25 Reset Existing Valve Box or Manhole Frame and Cover for Pavement Overlay, Installed and Complete-in-Place  Each  1  $      500.00  $                 500.00  $      300.00  $               300.00  $      200.00  $           200.00  $      134.00  $          134.00  $      150.00  $             150.00  $      150.00  $         150.00  $      500.00  $             500.00  $      217.00  $              217.00  $      370.00  $             370.00  $      750.00  $              750.00  $    1,100.00  $               1,100.00  $      200.00  $            200.00  $      750.00  $            750.00
26 12-inch Culvert Pipe  LF  40  $        90.00  $              3,600.00  $        40.00  $            1,600.00  $        20.00  $           800.00  $        47.50  $       1,900.00  $        12.00  $             480.00  $        50.00  $      2,000.00  $        70.12  $          2,804.80  $        49.40  $            1,976.00  $        32.00  $           1,280.00  $        72.00  $           2,880.00  $        31.00  $               1,240.00  $        40.00  $         1,600.00  $        58.41  $         2,336.40
27 15-inch Culvert Pipe  LF  40  $      100.00  $              4,000.00  $        45.00  $            1,800.00  $        22.00  $           880.00  $        51.00  $       2,040.00  $        15.00  $             600.00  $        60.00  $      2,400.00  $        74.35  $          2,974.00  $        53.40  $            2,136.00  $        33.00  $           1,320.00  $        75.00  $           3,000.00  $        38.00  $               1,520.00  $        40.00  $         1,600.00  $        60.01  $         2,400.40
28 18-inch Culvert Pipe  LF  40  $      125.00  $              5,000.00  $        55.00  $            2,200.00  $        24.00  $           960.00  $        57.00  $       2,280.00  $        20.00  $             800.00  $        70.00  $      2,800.00  $        86.62  $          3,464.80  $        71.50  $            2,860.00  $        35.00  $           1,400.00  $        80.00  $           3,200.00  $        43.00  $               1,720.00  $        40.00  $         1,600.00  $        65.20  $         2,608.00
29 8” DI Water Main, Installed Complete-in-Place  LF  570  $        70.00  $            39,900.00  $        35.00  $          19,950.00  $        62.70  $       35,739.00  $        75.37  $     42,960.90  $        50.00  $         28,500.00  $        80.00  $    45,600.00  $      149.69  $         85,323.30  $        63.00  $          35,910.00  $        28.00  $         15,960.00  $      120.00  $          68,400.00  $        46.00  $             26,220.00  $        60.00  $       34,200.00  $        46.64  $       26,584.80
30 Fire Hydrant Assemble, Type II-A  Each  1  $    4,000.00  $              4,000.00  $    4,000.00  $            4,000.00  $    3,850.00  $         3,850.00  $    3,981.00  $       3,981.00  $    2,900.00  $          2,900.00  $    4,800.00  $      4,800.00  $    4,872.50  $          4,872.50  $    6,000.00  $            6,000.00  $    3,528.00  $           3,528.00  $    4,000.00  $           4,000.00  $    3,876.00  $               3,876.00  $    3,500.00  $         3,500.00  $    3,805.19  $         3,805.19
31 3 Vacuum Sewer  Installed Complete-in-Place LF  1,350  $      130.00  $          175,500.00  $        35.00  $          47,250.00  $        44.50  $       60,075.00  $        48.00  $     64,800.00  $        47.00  $         63,450.00  $        40.00  $    54,000.00  $      110.00  $       148,500.00  $        67.40  $          90,990.00  $        22.00  $         29,700.00  $      110.00  $        148,500.00  $        54.00  $             72,900.00  $        90.00  $     121,500.00  $        33.41  $       45,103.50
32 4 Vacuum Sewer Installed Complete-in-Place LF  9,300  $        60.00  $          558,000.00  $        42.00  $        390,600.00  $        53.70  $     499,410.00  $        57.00  $    530,100.00  $        55.00  $       511,500.00  $        70.00  $  651,000.00  $      112.00  $    1,041,600.00  $        67.10  $        624,030.00  $        20.50  $       190,650.00  $        80.00  $        744,000.00  $        55.00  $           511,500.00  $        94.00  $     874,200.00  $        32.25  $      299,925.00
33 6 Vacuum Sewer Installed Complete-in-Place LF  4,480  $        80.00  $          358,400.00  $        61.00  $        273,280.00  $        60.70  $     271,936.00  $        64.00  $    286,720.00  $        62.00  $       277,760.00  $        80.00  $  358,400.00  $      114.00  $       510,720.00  $        67.70  $        303,296.00  $        25.00  $       112,000.00  $        82.00  $        367,360.00  $        56.00  $           250,880.00  $        98.00  $     439,040.00  $        37.51  $      168,044.80
34 4 Vacuum Sewer Isolation Valve and Gauge Tap " Each  4  $    1,500.00  $              6,000.00  $    1,000.00  $            4,000.00  $    2,500.00  $       10,000.00  $    2,418.00  $       9,672.00  $    1,400.00  $          5,600.00  $    3,500.00  $    14,000.00  $    1,932.00  $          7,728.00  $    2,570.00  $          10,280.00  $    1,344.00  $           5,376.00  $    2,000.00  $           8,000.00  $    1,653.00  $               6,612.00  $    1,500.00  $         6,000.00  $    1,870.60  $         7,482.40
35 6 Vacuum Sewer Isolation Valve and Gauge Tap " Each  2  $    2,000.00  $              4,000.00  $    1,200.00  $            2,400.00  $    2,800.00  $         5,600.00  $    2,708.00  $       5,416.00  $    1,600.00  $          3,200.00  $    4,200.00  $      8,400.00  $    2,072.00  $          4,144.00  $    2,900.00  $            5,800.00  $    1,510.00  $           3,020.00  $    2,200.00  $           4,400.00  $    1,833.00  $               3,666.00  $    1,700.00  $         3,400.00  $    2,079.60  $         4,159.20
36 DI Casing Pipe, Installed Complete-in-Place  LF  100  $      100.00  $            10,000.00  $        50.00  $            5,000.00  $        28.00  $         2,800.00  $        19.43  $       1,943.00  $          0.01  $                 1.00  $      130.00  $    13,000.00  $        75.00  $          7,500.00  $      293.00  $          29,300.00  $        68.00  $           6,800.00  $      125.00  $          12,500.00  $        82.00  $               8,200.00  $        30.00  $         3,000.00  $        46.21  $         4,621.00
37 End of Line Marker, Installed Complete-in-Place  Each  11  $      100.00  $              1,100.00  $      250.00  $            2,750.00  $      155.00  $         1,705.00  $        73.00  $          803.00  $        50.00  $             550.00  $      125.00  $      1,375.00  $      386.00  $          4,246.00  $      275.00  $            3,025.00  $      158.00  $           1,738.00  $      270.00  $           2,970.00  $      376.00  $               4,136.00  $        50.00  $            550.00  $      350.10  $         3,851.10
38 Shallow Vacuum Valve Pit and Collection Sump, Installed Complete in Place  Each  5  $    4,000.00  $            20,000.00  $    3,500.00  $          17,500.00  $    3,875.00  $       19,375.00  $    3,748.00  $     18,740.00  $    3,500.00  $         17,500.00  $    6,000.00  $    30,000.00  $    4,356.25  $         21,781.25  $    5,780.00  $          28,900.00  $    3,526.00  $         17,630.00  $    4,300.00  $          21,500.00  $    7,692.00  $             38,460.00  $    4,200.00  $       21,000.00  $    6,144.49  $       30,722.45
39 Standard Vacuum Valve Pit and Collection Sump, Installed Complete in Place  Each  16  $    7,500.00  $          120,000.00  $    3,500.00  $          56,000.00  $    4,000.00  $       64,000.00  $    3,868.80  $     61,900.80  $    4,800.00  $         76,800.00  $    7,500.00  $  120,000.00  $    4,515.00  $         72,240.00  $    5,920.00  $          94,720.00  $    3,757.00  $         60,112.00  $    6,000.00  $          96,000.00  $    7,820.00  $           125,120.00  $    5,400.00  $       86,400.00  $    6,435.48  $      102,967.68
40 Deep Vacuum Valve Pit and Collection Sump, Installed Complete in Place  Each  17  $    9,500.00  $          161,500.00  $    4,000.00  $          68,000.00  $    5,000.00  $       85,000.00  $    4,696.00  $     79,832.00  $    5,900.00  $       100,300.00  $    8,000.00  $  136,000.00  $    5,018.75  $         85,318.75  $    6,540.00  $        111,180.00  $    3,838.00  $         65,246.00  $    6,400.00  $        108,800.00  $    8,256.00  $           140,352.00  $    6,500.00  $     110,500.00  $    7,278.80  $      123,739.60
41 Vacuum Sewer Line Flushing and Testing  LS  1  $100,000.00  $          100,000.00  $  20,000.00  $          20,000.00  $    5,000.00  $         5,000.00  $    7,254.00  $       7,254.00  $    1,500.00  $          1,500.00  $    5,000.00  $      5,000.00  $  10,000.00  $         10,000.00  $  29,100.00  $          29,100.00  $  27,895.00  $         27,895.00  $  45,000.00  $          45,000.00  $  46,430.00  $             46,430.00  $    5,000.00  $         5,000.00  $  22,688.00  $       22,688.00
42 4” PVC Gravity Sewer Lateral, Installed Complete-in-Place  LF  3,350  $        50.00  $          167,500.00  $        39.00  $        130,650.00  $        55.70  $     186,595.00  $        59.00  $    197,650.00  $        38.00  $       127,300.00  $      125.00  $  418,750.00  $      100.00  $       335,000.00  $      104.00  $        348,400.00  $        24.00  $         80,400.00  $        40.00  $        134,000.00  $        10.50  $             35,175.00  $        50.00  $     167,500.00  $        34.75  $      116,412.50
43 6” PVC Gravity Sewer Lateral, Installed Complete-in-Place  LF  230  $        55.00  $            12,650.00  $        43.00  $            9,890.00  $        65.70  $       15,111.00  $        69.00  $     15,870.00  $        42.00  $          9,660.00  $      130.00  $    29,900.00  $      134.00  $         30,820.00  $      100.00  $          23,000.00  $        51.00  $         11,730.00  $        50.00  $          11,500.00  $        25.40  $               5,842.00  $        54.00  $       12,420.00  $        37.55  $         8,636.50
44 4” PVC Sewer Lateral Cleanout Assembly, Installed Complete-in-Place  Each  152  $      125.00  $            19,000.00  $      295.00  $          44,840.00  $      118.00  $       17,936.00  $        15.00  $       2,280.00  $      225.00  $         34,200.00  $      225.00  $    34,200.00  $      126.25  $         19,190.00  $      325.00  $          49,400.00  $      167.00  $         25,384.00  $      800.00  $        121,600.00  $      153.00  $             23,256.00  $      350.00  $       53,200.00  $      320.75  $       48,754.00
45 6” PVC Sewer Lateral Cleanout Assembly, Installed Complete-in-Place  Each  1  $      150.00  $                 150.00  $      395.00  $               395.00  $      122.00  $           122.00  $      146.00  $          146.00  $      300.00  $             300.00  $      250.00  $         250.00  $      200.00  $             200.00  $      627.00  $              627.00  $      187.00  $             187.00  $      850.00  $              850.00  $      160.00  $                  160.00  $      400.00  $            400.00  $      399.49  $            399.49
46 8” PVC Gravity Sewer Main, Installed Complete-in-Place  LF  2,230  $      210.00  $          468,300.00  $        75.00  $        167,250.00  $        95.70  $     213,411.00  $      171.28  $    381,954.40  $        60.00  $       133,800.00  $      260.00  $  579,800.00  $      126.29  $       281,626.70  $      191.00  $        425,930.00  $        38.00  $         84,740.00  $      170.00  $        379,100.00  $        70.90  $           158,107.00  $      100.00  $     223,000.00  $        41.26  $       92,009.80
47 48” Diameter Precast Concrete Manhole, Installed Complete-in-Place  Each  11  $      260.00  $              2,860.00  $    4,000.00  $          44,000.00  $    3,200.00  $       35,200.00  $    6,448.00  $     70,928.00  $    4,200.00  $         46,200.00  $    8,000.00  $    88,000.00  $  12,695.00  $       139,645.00  $    9,980.00  $        109,780.00  $    3,175.00  $         34,925.00  $    3,400.00  $          37,400.00  $    2,293.00  $             25,223.00  $    5,000.00  $       55,000.00  $    3,802.18  $       41,823.98
48 Watertight Manhole Frame and Cover, Installed Complete-in-Place  Each  11  $    8,000.00  $            88,000.00  $      600.00  $            6,600.00  $      700.00  $         7,700.00  $      411.27  $       4,523.97  $      400.00  $          4,400.00  $      625.00  $      6,875.00  $      535.00  $          5,885.00  $    1,350.00  $          14,850.00  $      602.00  $           6,622.00  $      965.00  $          10,615.00  $    1,915.00  $             21,065.00  $      450.00  $         4,950.00  $      562.55  $         6,188.05
49 2” PVC Force Main, Installed Complete-in-Place  LF  1,600  $        38.00  $            60,800.00  $        16.00  $          25,600.00  $        55.70  $       89,120.00  $        41.92  $     67,072.00  $          8.00  $         12,800.00  $        20.00  $    32,000.00  $      104.00  $       166,400.00  $        19.70  $          31,520.00  $          7.00  $         11,200.00  $        34.00  $          54,400.00  $        22.50  $             36,000.00  $        18.00  $       28,800.00  $        35.55  $       56,880.00
50 Manual Air Relief Valve, Installed Complete-in-Place  Each  1  $    1,200.00  $              1,200.00  $    1,500.00  $            1,500.00  $      350.00  $           350.00  $      699.00  $          699.00  $      900.00  $             900.00  $    2,500.00  $      2,500.00  $      976.25  $             976.25  $    1,320.00  $            1,320.00  $      789.00  $             789.00  $    1,600.00  $           1,600.00  $    1,670.00  $               1,670.00  $      500.00  $            500.00  $      994.44  $            994.44
51 2” Force Main Gate Valve, Installed Complete-in-Place  Each  1  $      750.00  $                 750.00  $      600.00  $               600.00  $      750.00  $           750.00  $      602.00  $          602.00  $      600.00  $             600.00  $    1,500.00  $      1,500.00  $      758.75  $             758.75  $    1,190.00  $            1,190.00  $      489.00  $             489.00  $    1,250.00  $           1,250.00  $      742.00  $                  742.00  $      300.00  $            300.00  $      556.09  $            556.09
52 Tracer Wire Access Point  Each  1  $      200.00  $                 200.00  $      200.00  $               200.00  $    1,575.00  $         1,575.00  $      156.00  $          156.00  $      300.00  $             300.00  $    1,500.00  $      1,500.00  $      210.00  $             210.00  $    2,670.00  $            2,670.00  $      540.00  $             540.00  $      220.00  $              220.00  $    1,318.00  $               1,318.00  $      200.00  $            200.00  $      350.00  $            350.00
53 Horizontal Directional Drill  LS  1  $222,240.00  $          222,240.00  $  78,000.00  $          78,000.00  $  41,000.00  $       41,000.00  $  41,440.00  $     41,440.00  $  84,000.00  $         84,000.00  $  80,000.00  $    80,000.00  $163,265.00  $       163,265.00  $227,000.00  $        227,000.00  $189,530.00  $       189,530.00  $180,000.00  $        180,000.00  $427,800.00  $           427,800.00  $  55,000.00  $       55,000.00  $  54,887.38  $       54,887.38
54 Grinder Force Main Cleanout & Valve Vault, Installed Complete-in-Place  Each  2  $    8,500.00  $            17,000.00  $    1,500.00  $            3,000.00  $    1,500.00  $         3,000.00  $    1,310.00  $       2,620.00  $      900.00  $          1,800.00  $    1,500.00  $      3,000.00  $    5,300.00  $         10,600.00  $    4,930.00  $            9,860.00  $    3,280.00  $           6,560.00  $    2,000.00  $           4,000.00  $    5,216.00  $             10,432.00  $    4,000.00  $         8,000.00  $    1,263.19  $         2,526.38
55 Vacuum Dual Buffer Tank, Installed Complete-in-Place  Each  1  $  24,000.00  $            24,000.00  $  50,000.00  $          50,000.00  $    8,000.00  $         8,000.00  $  12,480.00  $     12,480.00  $    9,000.00  $          9,000.00  $  20,000.00  $    20,000.00  $  14,707.50  $         14,707.50  $  38,000.00  $          38,000.00  $  23,200.00  $         23,200.00  $  28,000.00  $          28,000.00  $  10,462.00  $             10,462.00  $  20,000.00  $       20,000.00  $  10,430.49  $       10,430.49
56 Grinder Pump Station, Installed Complete-in-Place  LS  1  $271,400.00  $          271,400.00  $280,000.00  $        280,000.00  $163,000.00  $     163,000.00  $230,534.23  $    230,534.23  $150,000.00  $       150,000.00  $330,000.00  $  330,000.00  $276,477.19  $       276,477.19  $336,000.00  $        336,000.00  $150,000.00  $       150,000.00  $215,000.00  $        215,000.00  $187,015.00  $           187,015.00  $160,000.00  $     160,000.00  $120,384.23  $      120,384.23
TOTAL:    $        3,906,703.50    $      2,777,321.00    $  2,470,935.00    $ 2,868,434.62    $    2,024,157.00    $4,127,140.50    $    4,362,775.39    $     4,136,984.00    $    2,305,212.00    $     4,654,100.00    $         4,681,908.00    $   2,940,365.00    $   2,398,861.44
            Bid form submitted reads:  $  2,471,205.00  $ 2,947,521.23  $    4,362,805.39  $    2,248,512.00  $         4,643,798.00  $   2,920,115.00  $   2,401,861.44
                   Difference from form  $          (270.00)  $    (79,086.61)  $              (30.00)  $         56,700.00  $             38,110.00  $       20,250.00  $        (3,000.00)