Brandywine Drainage Phase Improvements Project |
Burcher Road and Allens Mill Road portion of the
project is now out to bid. Construction in the area is
anticipated to begin this summer. The design of the remainder
of the Brandywine Drainage project is complete. It is
anticipated that it will go out to bid in the late Fall. For
questions, please contact the County’s Project Engineer, Joe
Brogan, at 890-3831. |
|
Egdehill Drainage Improvement Project |
Serves the portion of the Edgehill neighborhood
roughly south of York-Warwick Drive. The study phase of this
project is complete. The engineering firm is working on the
scope and fee for design plans. The design of the proposed
improvements should begin shortly. For questions, please contact
the County’s Project Engineer, Joe Brogan, at 890-3831. |
|
Moores Creek Phase I Drainage Improvement Project |
Project is
complete except for monitoring. |
|
Moores Creek Phase IIA Drainage Improvement
Project |
(Big Bethel Road
box culverts) The County received the 95% plans on March 27, and
the specs on March 28. The Joint Permit Application was
submitted to VMRC on March 31, 2008. We anticipate going to
construction in late 2008 depending on ACOE and DEQ permitting
requirements. |
|
Moores Creek Phase IIB Drainage Improvement
Project |
(Victory Blvd
drainage pipe) The County provided comments to Baker on the 75%
plans in March 2008. The 75% plans will be modified and sent to
VDOT, NNWW, HRSD, etc. We anticipate going to construction in
late 2008/early 2009 depending on the ACOE and DEQ permitting
requirements |
|
Moores Creek Phase IIC Drainage Improvement
Project |
(Homestead
BMP/Dawn Place) The survey is complete and the wetlands
delineation has been field checked by the ACOE but we not
received a confirmed yet. We anticipate beginning design in the
late summer of 2008. |
|
Marlbank Farm Sanitary Sewer Project |
The Project is complete |
|
York Point Phase I Sanitary Sewer Project |
Construction of the vacuum pump station and the
pipe line work is nearing completion. Once the pavement and
roadway restoration is completed, letters will be issued (June
2008) to homeowners giving notice when connection is available.
For questions, please contact the County’s Project Engineer,
Michael Elam, at 890-3763. |
|
York Point Phase II Sanitary Sewer Project
|
Phase II includes Smoots Lane, DeAlba Lane,
Wildey Road, Presson Road, Hansford Lane and Bay Tree Beach
Road. Construction of Phase II is expected to be completed in
the Spring of 2009. |
|
Queens Lake Sanitary Sewer Project |
Design of Phase I (Gravity Portion, Pump Station
& Force Main) is nearing completion. Progress has been slow due
to acquiring the Pump Station site. A public meeting will be
scheduled soon to discuss the Phase I design.
|
|
Wolftrap Road Sanitary Sewer Project |
Survey crews are currently working gathering
data/elevations. |
|
Lightfoot/ Skimino & Banburry Water System |
New well has been operational since March 24,
2008. Within 30 days test and inspections will be performed at
Well Site #5. After the inspections, a 90 day Public Education/
Public Relations process will commence to notify all our water
customers about the transfer of our water facilities to Newport
News Waterworks. |