ARTICLE II. STORMWATER MANAGEMENT PROGRAM
PROCEDURES AND REQUIREMENTS
Sec. 23.3-16.
Sequence of construction and record drawings.
(a) Unless otherwise approved, in any land
development or land development project, any required stormwater system
shall be constructed prior to the construction of any required sanitary
sewer system.
(b) Record Drawings are required for all components of the stormwater
system. The record drawings shall be appropriately sealed and signed by a
licensed professional in adherence to all minimum standards and requirements
pertaining to the practice of that profession. The record drawings shall:
(1) Be of the same sheet size; format,
scale, etc. as the approved stormwater management plans;
(2) Show the as-built condition of the
stormwater system calling attention to any changes from the approved
drawings;
(3) Give the actual dimensions of
components such as length of pipe, ditch, etc.;
(4) Provide elevations for all rims, inverts,
channel bottoms, outfalls, pond cross-sections, structures and all other
elevation sensitive components of the system; and
(5) Contain a certification stating that
the stormwater system has been constructed in accordance with the plan and
that the system is functioning as designed.
(c) Prior to the issuance of building permits for above ground
structures, preliminary record drawings of the completed stormwater system
must be submitted for approval.
(d) Prior to the completion of the project and prior to the issuance
of the “Certificate of Occupancy” for any structure, final record drawings
shall be submitted and approved.
(Ord.
No. 06-17, 7/18/06) |