Sec. 23.2-15.
Granting exceptions.
The
Chesapeake Bay Board may grant exceptions as set forth herein. Exceptions
granted by the board will become null and void if the proposed project is
not completed within five years. The board shall make its determination
within 65 days of the hearing; and if the board fails to act within this
time frame the application shall be deemed to be approved.
(Ord.
No. 05-13(R), 5/17/05) |