(a) Any person desiring to connect to facilities of the county shall
pay the fees set forth in this article prior to making connection to such facilities.
Connection to any public water system shall be voluntary for all premises qualifying under
Section 22-81(b) of this chapter, and mandatory for all others.
(b) Where the county currently owns the public water system or the
governing body on or after January 1, 1988, has completed the extension of, or
participated financially in the extension of, public water to areas of the county which
have not previously been served, the owner of any premises desiring to be served shall pay
a connection fee as set forth in Section 22-99 of this chapter. If paid within ninety (90)
days of notification that service exists the fee shall be the initial fee set forth in
Section 22-99. After such time the regular connection fee shall apply except to those
connections to facilities of the county which were completed after January 1, 1988, and
prior to January 1, 1989, and in those cases the initial connection fee shall continue to
be charged.
(c) On or after January 1, 1996, when a developer extends facilities
owned by the county or, facilities of the county, which facilities of the county were
completed after January 1, 1988, and are no longer owned by the county, the owner of any
premises desiring to be served shall pay a system facility charge as set forth in Section
22-99 of this chapter. If paid within ninety (90) days of notification that service
exists, the fee shall be the initial fee set forth in Section 22-99. After such time the
regular fee shall apply.
(d) Where a developer constructs a public pump and well system pursuant
to Section 22-89, the developer shall pay to the county at the time of dedication an
initial system facility charge as set forth in Section 22-99 for each proposed connection
to the system.
(e) Where the county purchases or acquires an existing water system
after January 1, 1996, and the system is to be upgraded to meet county standards, an
initial connection fee shall be paid by all existing users within ninety (90) days of the
completion of the improvements. Connections made