ARTICLE IV. CONSTRUCTION
AND EXTENSION OF PUBLIC SEWER SYSTEMS
Sec. 18.1-52. Application, certificate to construct, inspection and
payment of fees required.
(a) Certificates to construct. Construction
of or extensions to public sewer systems shall not begin until a certificate
to construct has been issued by the county administrator. The construction
of building sewers which serve multiple dwellings or structures or which
extend off-site shall also require a certificate to construct.
(b) Applications. Applications for a
certificate to construct shall be submitted to the County and accompanied by
a minimum of four (4) copies of plans and specifications prepared by a
qualified licensed engineer or land surveyor practicing within the areas of
competence prescribed by section 54.1-408 et seq of the Code of Virginia
together with any other relevant contract documents and a plan review fee of
one-hundred and twenty-five dollars ($125.00).
(c) Issuance. Upon approval of the plans,
specifications, and contract documents and upon payment of required
inspection fees, the county administrator shall issue a certificate to
construct.
(d) Fees. A certificate to construct shall
not be issued until inspection fees in the amount of
three hundred dollars ($300.00) plus one dollar and
seventy-five cents ($1.75) per
foot for every foot of eight-inch or larger gravity sewer installed and one
dollar and seventy-five cents ($1.75) per foot for every foot of two-inch or larger
force main installed and one dollar and seventy-five cents ($1.75) per foot for every
foot of vacuum sewer installed have been paid. In the case of building
sewers required to be inspected pursuant to the provisions of section
18.1-24 of this chapter, an inspection fee shall be charged in the amount of
one hundred and seventy-five dollars ($175.00) plus one dollar and
seventy-five
cents ($1.75) per foot for every foot of building sewer installed. The fees
set forth in this subsection may not be reduced and are not refundable.
(e) Inspection. The installation of public
sewer systems and building sewers required to have a certificate to
construct shall be inspected by the county and no part of such facilities
shall be covered or obscured prior to inspection and approval by the county.
(f) Service laterals. Service laterals, as
approved, shall be provided by the applicant and installed at the time of
construction.
(g) Connection to system regulated. No
connection between the existing public sewer system and new sewer
construction shall be made until all required connection fees have been paid
and all such construction has been approved by the county.
(Ord. No. 02-6(R-1), 7/16/02;
Ord. No. 07-22, 1218/07) |